Daggett sits in an area outside an organized wholesale market; what follows is the screening-grade grid picture for Daggett, Utah, drawn from public datasets. Counting from the mapped infrastructure, Daggett holds 1 mapped substation and reaches 230 kV. Daggett is covered by 4 retail service territories, including BRIDGER VALLEY ELEC ASSN, INC, MOON LAKE ELECTRIC ASSN INC, PACIFICORP.
Grid position at a glance
- Serving utilities
- BRIDGER VALLEY ELEC ASSN, INC, MOON LAKE ELECTRIC ASSN INC, PACIFICORP, WAPA-- WESTERN AREA POWER ADMINISTRATION
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 230 kV
- Substations in county
- 1
- Industrial retail rate
- 8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 4 serving utilities: 3.1 to 10.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 1,410 lb CO2/MWh
- Water withdrawals
- 20 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 7,746 employed in construction within ~120 km (5 of 6 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Daggett
Everything here about Daggett, Utah comes from public federal and state records, with the gaps left visible. Daggett reaches 230 kV at its highest mapped voltage, a transmission class that can carry a substantial interconnection where capacity exists. Daggett, Utah carries a thin 1-substation footprint in the mapped layer, concentrating where a connection could land.
Daggett, Utah is not inside an organized market, which leaves interconnection to the utility and bilateral contracts. The rate for Daggett is the 8.4 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Daggett, reported per-utility industrial rates cover 3 of 4 serving utilities: 3.1 to 10.4¢/kWh, offered only as context beneath the state figure.
No interconnection-queue project is on record for Daggett, Utah in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Daggett, Utah has no EIA-860M generation on file, which reads as zero rather than as a gap. The balancing authority covering Daggett carries a grid carbon intensity of 1,410.035 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Daggett are 20.12 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Daggett, some 7,746 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Daggett are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Daggett, Utah together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Daggett, Utah is an address-level interconnection study; the county figures here only narrow where to look. For Daggett, Utah, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.