Power by county
Duchesne, UT: data center power outlook
The grid around Duchesne, Utah is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Duchesne the mapped layer shows 29 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Duchesne is split among 4 utilities, among them BRIDGER VALLEY ELEC ASSN, INC, MOON LAKE ELECTRIC ASSN INC, PACIFICORP.
Grid position at a glance
- Serving utilities
- BRIDGER VALLEY ELEC ASSN, INC, MOON LAKE ELECTRIC ASSN INC, PACIFICORP, WAPA-- WESTERN AREA POWER ADMINISTRATION
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 345 kV
- Substations in county
- 29
- Industrial retail rate
- 8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 4 serving utilities: 3.1 to 10.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 1,410 lb CO2/MWh
- Water withdrawals
- 314 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 39,432 employed in construction within ~120 km (7 of 8 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Duchesne
The sections below set out what public data shows about siting a large electrical load in Duchesne, Utah. At 345 kV, Duchesne carries high-voltage transmission at its strongest mapped point. Duchesne contains 29 mapped substations, a dense footprint that spreads interconnection options across many points.
There is no organized wholesale market over Duchesne, Utah; arrangements run through the serving utility instead. Duchesne carries the state industrial average retail rate of 8.4 cents per kWh from EIA-861, applied statewide. For Duchesne, the per-utility spread is 3 of 4 serving utilities: 3.1 to 10.4¢/kWh, which qualifies but never replaces the state average.
Duchesne, Utah shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. For Duchesne, Utah, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Duchesne shows 1,410.035 lb CO2 per MWh.
For Duchesne, the USGS 2015 compilation records 314.12 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Duchesne sits within commuting range of roughly 39,432 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Duchesne here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Duchesne, Utah settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Duchesne, Utah requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Duchesne, Utah are logged directly below, so each figure on this page can be traced back to its public dataset.