The grid around Garfield, Utah is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Garfield the mapped layer shows 18 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Garfield is split among 3 utilities, among them GARKANE ENERGY COOP, INC, PACIFICORP, WAPA-- WESTERN AREA POWER ADMINISTRATION.

Grid position at a glance

Serving utilities
GARKANE ENERGY COOP, INC, PACIFICORP, WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
345 kV
Substations in county
18
Industrial retail rate
8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 serving utilities: 3.1 to 7.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,410 lb CO2/MWh
Water withdrawals
57 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
1,011 employed in construction within ~120 km (4 of 5 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Garfield

Read on for the public power picture of Garfield in Utah, assembled for data center siting. At 345 kV, Garfield carries high-voltage transmission at its strongest mapped point. Garfield contains 18 mapped substations, a moderate footprint spread across the service area.

There is no organized wholesale market over Garfield, Utah; arrangements run through the serving utility instead. Garfield carries the state industrial average retail rate of 8.4 cents per kWh from EIA-861, applied statewide. For Garfield, the per-utility spread is 3 serving utilities: 3.1 to 7.8¢/kWh, which qualifies but never replaces the state average.

Garfield, Utah has nothing in the interconnection queue across the feeds covered here, quiet or uningested. For Garfield, Utah, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Garfield shows 1,410.035 lb CO2 per MWh.

For Garfield, the USGS 2015 compilation records 57.4 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Garfield sits within commuting range of roughly 1,011 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Garfield here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Garfield, Utah settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Garfield, Utah requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Garfield, Utah are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources