Power by county

Augusta, VA: data center power outlook

Augusta, Virginia is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Augusta carries 18 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Augusta spans 5 utilities, with BARC ELECTRIC COOP INC, CENTRAL VIRGINIA ELECTRIC COOP, MONONGAHELA POWER CO among those mapped.

Grid position at a glance

Serving utilities
BARC ELECTRIC COOP INC, CENTRAL VIRGINIA ELECTRIC COOP, MONONGAHELA POWER CO, SHENANDOAH VALLEY ELEC COOP, VIRGINIA ELECTRIC & POWER CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
500 kV
Substations in county
18
Industrial retail rate
9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 5 serving utilities: 6.0 to 9.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
11 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
16 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
28,662 employed in construction within ~120 km (36 of 43 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Augusta

The material below frames Augusta, Virginia for a prospective large load, drawing only on public sources. Grid access in Augusta extends to 500 kV, a high-voltage line class. The mapped layer places 18 substations across Augusta, a moderate density.

Interconnection over Augusta runs through the PJM market (PJM Interconnection) and its rules. For Augusta, the rate shown is the state industrial average of 9.4 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Augusta that report an industrial rate span 3 of 5 serving utilities: 6.0 to 9.6¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Augusta, Virginia in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M records 11 MW planned or under construction for Augusta. Augusta sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.

Augusta withdrew 16.12 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 28,662 people are employed in construction within a 120 km commute of Augusta (BLS QCEW), which frames staffing distance rather than free labour.

For Augusta, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Augusta, Virginia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Augusta, Virginia, a specific address needs its own interconnection study, which this page does not attempt. The figures for Augusta, Virginia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.