Charlotte, VA: data center power outlook

Charlotte, Virginia is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Charlotte carries 10 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Charlotte spans 3 utilities, with MECKLENBURG ELECTRIC COOPERATIVE, SOUTHSIDE ELECTRIC COOP, INC, VIRGINIA ELECTRIC & POWER CO among those mapped.

Grid position at a glance

Serving utilities
MECKLENBURG ELECTRIC COOPERATIVE, SOUTHSIDE ELECTRIC COOP, INC, VIRGINIA ELECTRIC & POWER CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
500 kV
Substations in county
10
Industrial retail rate
9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 serving utilities: 6.0 to 9.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
317 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
1.5 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
50,928 employed in construction within ~120 km (41 of 45 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Charlotte

What follows is a screening-grade read of Charlotte, Virginia, built only from named public datasets. Grid access in Charlotte extends to 500 kV, a high-voltage line class. The mapped layer places 10 substations across Charlotte, a moderate density.

Interconnection over Charlotte runs through the PJM market (PJM Interconnection) and its rules. For Charlotte, the rate shown is the state industrial average of 9.4 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Charlotte that report an industrial rate span 3 serving utilities: 6.0 to 9.2¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Charlotte, Virginia in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M records 317 MW planned or under construction for Charlotte. Charlotte sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.

Charlotte withdrew 1.47 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 50,928 people are employed in construction within a 120 km commute of Charlotte (BLS QCEW), which frames staffing distance rather than free labour.

For Charlotte, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Charlotte, Virginia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Charlotte, Virginia, a specific address needs its own interconnection study, which this page does not attempt. The figures for Charlotte, Virginia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.