Power by county

Chesterfield, VA: data center power outlook

The grid around Chesterfield, Virginia is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Chesterfield the mapped layer shows 39 mapped substations, with grid access reaching 500 kV at its strongest point. Retail service across Chesterfield is split among 2 utilities, among them SOUTHSIDE ELECTRIC COOP, INC, VIRGINIA ELECTRIC & POWER CO.

Grid position at a glance

Serving utilities
SOUTHSIDE ELECTRIC COOP, INC, VIRGINIA ELECTRIC & POWER CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
500 kV
Substations in county
39
Industrial retail rate
9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 serving utilities: 6.0 to 9.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
1,163 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
951 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
69,321 employed in construction within ~120 km (54 of 57 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Chesterfield

Read on for the public power picture of Chesterfield in Virginia, assembled for data center siting. At 500 kV, Chesterfield carries high-voltage transmission at its strongest mapped point. Chesterfield contains 39 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Chesterfield clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Chesterfield carries the state industrial average retail rate of 9.4 cents per kWh from EIA-861, applied statewide. For Chesterfield, the per-utility spread is 2 serving utilities: 6.0 to 9.2¢/kWh, which qualifies but never replaces the state average.

For Chesterfield, Virginia, no queued project appears in the feeds currently covered. In Chesterfield, 1,162.6 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Chesterfield shows 716.09 lb CO2 per MWh.

For Chesterfield, the USGS 2015 compilation records 951.03 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Chesterfield sits within commuting range of roughly 69,321 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Chesterfield here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Chesterfield, Virginia settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Chesterfield, Virginia requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Chesterfield, Virginia are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources