Grant, WA: data center power outlook

The grid around Grant, Washington is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Grant the mapped layer shows 111 mapped substations, with grid access reaching 500 kV at its strongest point. Retail service across Grant is split among 11 utilities, among them AVISTA CORP, BENTON RURAL ELECTRIC ASSN, BIG BEND ELECTRIC COOP, INC.

Grid position at a glance

Serving utilities
AVISTA CORP, BENTON RURAL ELECTRIC ASSN, BIG BEND ELECTRIC COOP, INC, BONNEVILLE POWER ADMINISTRATION, CITY OF COULEE DAM - (WA), INLAND POWER & LIGHT COMPANY, NESPELEM VALLEY ELEC COOP, INC, PUD NO 1 OF BENTON COUNTY, PUD NO 1 OF DOUGLAS COUNTY, PUD NO 1 OF KITTITAS COUNTY, PUD NO 2 OF GRANT COUNTY
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
111
Industrial retail rate
6.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
8 of 11 serving utilities: 1.3 to 7.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
650 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
0 lb CO2/MWh
Water withdrawals
871 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
22,686 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Grant

Read on for the public power picture of Grant in Washington, assembled for data center siting. At 500 kV, Grant carries high-voltage transmission at its strongest mapped point. Grant contains 111 mapped substations, a dense footprint that spreads interconnection options across many points.

There is no organized wholesale market over Grant, Washington; arrangements run through the serving utility instead. Grant carries the state industrial average retail rate of 6.9 cents per kWh from EIA-861, applied statewide. For Grant, the per-utility spread is 8 of 11 serving utilities: 1.3 to 7.8¢/kWh, which qualifies but never replaces the state average.

Grant, Washington has nothing in the interconnection queue across the feeds covered here, quiet or uningested. In Grant, 650 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Grant shows 0 lb CO2 per MWh.

For Grant, the USGS 2015 compilation records 871.24 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Grant sits within commuting range of roughly 22,686 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Grant here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Grant, Washington settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Grant, Washington requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Grant, Washington are logged directly below, so each figure on this page can be traced back to its public dataset.