Marshall, WV: data center power outlook

The grid around Marshall, West Virginia is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Marshall the mapped layer shows 49 mapped substations, with grid access reaching 765 kV at its strongest point. Retail service across Marshall is split among 6 utilities, among them APPALACHIAN POWER CO, MONONGAHELA POWER CO, OHIO POWER CO.

Grid position at a glance

Serving utilities
APPALACHIAN POWER CO, MONONGAHELA POWER CO, OHIO POWER CO, SOUTH CENTRAL POWER COMPANY, WEST PENN POWER COMPANY, WHEELING POWER CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
765 kV
Substations in county
49
Industrial retail rate
8.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 6 serving utilities: 7.2 to 8.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
200 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
75,040 employed in construction within ~120 km (37 of 39 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Marshall

The sections below set out what public data shows about siting a large electrical load in Marshall, West Virginia. At 765 kV, Marshall carries extra-high-voltage transmission at its strongest mapped point. Marshall contains 49 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Marshall clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Marshall carries the state industrial average retail rate of 8.1 cents per kWh from EIA-861, applied statewide. For Marshall, the per-utility spread is 3 of 6 serving utilities: 7.2 to 8.8¢/kWh, which qualifies but never replaces the state average.

For Marshall, West Virginia, no queued project appears in the feeds currently covered. The federal EIA-860M inventory files no planned or under-construction generation in Marshall, West Virginia, a real zero rather than a gap. In eGRID, the balancing authority over Marshall shows 716.09 lb CO2 per MWh.

For Marshall, the USGS 2015 compilation records 199.99 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Marshall sits within commuting range of roughly 75,040 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Marshall here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Marshall, West Virginia settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Marshall, West Virginia requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Marshall, West Virginia are logged directly below, so each figure on this page can be traced back to its public dataset.