Power by county
Mineral, WV: data center power outlook
For Mineral, West Virginia, the public grid picture begins with its place in the PJM market (PJM Interconnection) and the infrastructure mapped inside the county. Grid access across Mineral tops out at 500 kV, over a footprint of 11 mapped substations. In Mineral, 2 utilities share the retail territory, among them MONONGAHELA POWER CO, THE POTOMAC EDISON COMPANY.
Grid position at a glance
- Serving utilities
- MONONGAHELA POWER CO, THE POTOMAC EDISON COMPANY
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 500 kV
- Substations in county
- 11
- Industrial retail rate
- 8.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 serving utilities: 7.4 to 7.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 2.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 58,730 employed in construction within ~120 km (31 of 34 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Mineral
For Mineral, West Virginia, the following sections turn public grid records into a siting-oriented summary. The highest mapped voltage in Mineral is 500 kV, in the high-voltage transmission class. Mineral carries 11 substations in the mapped layer, spread across the county.
For Mineral, the PJM market (PJM Interconnection) is the operator that handles interconnection and capacity. The state industrial average retail rate is 8.1 cents per kWh, drawn from EIA-861 and applied to Mineral at the state level rather than as a county rate. The serving utilities in Mineral that publish a rate range 2 serving utilities: 7.4 to 7.7¢/kWh, a spread kept separate from the state average.
Mineral, West Virginia shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. The federal EIA-860M inventory files no planned or under-construction generation in Mineral, West Virginia, a real zero rather than a gap. Grid carbon intensity for Mineral, via its balancing authority, is 716.09 lb CO2 per MWh in eGRID.
USGS 2015 puts freshwater withdrawals across Mineral at 2.61 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Mineral, about 58,730 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.
Read the Mineral figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Mineral, West Virginia qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Mineral, West Virginia turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Mineral, West Virginia traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.