Power by county
Oneida, WI: data center power outlook
The grid around Oneida, Wisconsin is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Oneida the mapped layer shows 8 mapped substations, with grid access reaching 115 kV at its strongest point. Retail service across Oneida is split among 5 utilities, among them BAYFIELD ELECTRIC COOP, INC, NORTHERN STATES POWER CO, PRICE ELECTRIC COOP INC.
Grid position at a glance
- Serving utilities
- BAYFIELD ELECTRIC COOP, INC, NORTHERN STATES POWER CO, PRICE ELECTRIC COOP INC, WISCONSIN PUBLIC SERVICE CORP, WPPI ENERGY
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 115 kV
- Substations in county
- 8
- Industrial retail rate
- 8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 5 serving utilities: 7.2 to 8.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 27 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 8,625 employed in construction within ~120 km (16 of 17 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Oneida
The sections below set out what public data shows about siting a large electrical load in Oneida, Wisconsin. Transmission-class access reaches 115 kV in Oneida at its strongest mapped point. Oneida contains 8 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Oneida clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Oneida carries the state industrial average retail rate of 8.9 cents per kWh from EIA-861, applied statewide. For Oneida, the per-utility spread is 2 of 5 serving utilities: 7.2 to 8.5¢/kWh, which qualifies but never replaces the state average.
Oneida, Wisconsin shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. The federal EIA-860M inventory files no planned or under-construction generation in Oneida, Wisconsin, a real zero rather than a gap. In eGRID, the balancing authority over Oneida shows 981.982 lb CO2 per MWh.
For Oneida, the USGS 2015 compilation records 26.98 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Oneida sits within commuting range of roughly 8,625 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Oneida here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Oneida, Wisconsin settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Oneida, Wisconsin requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Oneida, Wisconsin are logged directly below, so each figure on this page can be traced back to its public dataset.