Park, WY: data center power outlook
Park, Wyoming is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Park carries 38 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Park spans 11 utilities, with BEARTOOTH ELECTRIC COOP, INC, BIG HORN RURAL ELECTRIC CO, CITY OF CODY among those mapped.
Grid position at a glance
- Serving utilities
- BEARTOOTH ELECTRIC COOP, INC, BIG HORN RURAL ELECTRIC CO, CITY OF CODY, CITY OF POWELL - (WY), GARLAND LIGHT & POWER COMPANY, HIGH PLAINS POWER INC, LOWER VALLEY ENERGY INC, NORTHWESTERN ENERGY LLC - (MT), PACIFICORP, WAPA-- WESTERN AREA POWER ADMINISTRATION, WILLWOOD LIGHT & POWER COMPANY
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 230 kV
- Substations in county
- 38
- Industrial retail rate
- 8.7¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 11 serving utilities: 5.3 to 8.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 1,410 lb CO2/MWh
- Water withdrawals
- 618 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 4,842 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Park
The material below frames Park, Wyoming for a prospective large load, drawing only on public sources. At 230 kV, Park sits in the transmission class that a large load would look to. The mapped layer packs 38 substations into Park, a dense spread of options.
Park, Wyoming is not inside an organized market, which leaves interconnection to the utility and bilateral contracts. For Park, the rate shown is the state industrial average of 8.7 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Park that report an industrial rate span 3 of 11 serving utilities: 5.3 to 8.2¢/kWh, shown as context and never as the county rate.
Across the covered feeds, Park, Wyoming carries no interconnection-queue project, from either real quiet or a feed not yet loaded. EIA-860M lists nothing planned or under construction for Park, Wyoming, which is a national filing and so a real zero. Park sits under a balancing authority that eGRID puts at 1,410.035 lb CO2 per MWh.
Park withdrew 618.21 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 4,842 people are employed in construction within a 120 km commute of Park (BLS QCEW), which frames staffing distance rather than free labour.
For Park, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Park, Wyoming describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Park, Wyoming, a specific address needs its own interconnection study, which this page does not attempt. The figures for Park, Wyoming refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.